ODOT gives updates on District 2 projects

Sep 3, 2025 | Around Ottawa County | 0 comments

Craig Palmer, left, talks with an ODOT representative about the State Route 163 shoreline revetment project that could impact his home. (Photo by Sheri Trusty)

BY SHERI TRUSTY

PORT CLINTON – Craig and Kim Palmer were concerned that the lake view from their condo on West Lakeshore Dr. would be obscured by an upcoming Ohio Department of Transportation (ODOT) District 2 project, so they attended the Ottawa County fall projects information session hosted by ODOT at Liberty Aviation Center on Aug. 27. The informational open house highlighted several fall projects, including the State Route 163 shoreline revetment project that would impact the Palmer’s home.

The focus of the shoreline revetment project is repairing 3,100 feet of retaining wall along the north side of the West Lakeshore Dr. portion of State Route 163 that stretches between Richey Rd. and Dock’s Beach House bar and grill. Construction is tentatively scheduled to begin on Oct. 1 and is estimated to be completed by May 31.

A temporary traffic signal will be installed to maintain traffic both ways, one direction at a time. Access to properties will be maintained, and property owners will be given 24-hour notice about driveway closures.

ODOT District 2 Public Information Officer, Kelsie Hoagland, said the purpose of the project is to keep the lake from encroaching upon the roadway.

“They’ll use large stones, built several feet up,” Hoagland said.

ODOT District 2 Public Information Officer, Kelsie Hoagland, helped host a public informational open house about fall projects on Aug. 27. (Photo by Sheri Trusty)

Hoagland said the project will impact the view of the lake from the ground, but the Palmers were told the wall would not be built higher than the tallest stones that are already in place. Craig is the president of their condo association at The Admiralty, so the Palmers were worried about their neighbors as well as themselves. Kim walked away with some of her worries assuaged.

“I feel better because the big concern was how high the wall was going to be and if it would restrict our lake view,” she said. “They told me it shouldn’t be higher than some of the tall rocks that are out there now. I’m glad because people move out here because they love the lake.”

Kim was also worried about accessing her drive during the project but was told that one active driveway per property would remain open. The project will begin and end outside the tourist season, which will help eliminate traffic congestion.

“I’m glad they are doing this in the slow season,” Kim said.

While the Palmers were most concerned about the revetment project, many people attended the open house to learn about the new roundabout that will be installed at the intersection of State Route 269 and S. Danbury Rd. A traffic study of the area implemented between 2017 and 2019 showed eight total crashes, with five of them being injury crashes. In the post-study period, from 2020 to the present, 13 total crashes occurred at the intersection, including eight injury crashes and one fatality.

“There is a history of crash patterns at this location,” Hoagland said. “Eliminating conflict points is a top priority.”

A new roundabout that will be installed at the intersection of State Route 269 and S. Danbury Rd. will transform a confusing and dangerous area of roadway. (Photo by Sheri Trusty)

The State Route 269/S. Danbury Rd. roundabout project will be completed in two phases. Phase 1 will begin on Sept. 2 and run through April. During that time, all northbound lanes on State Route 269 will be closed, but motorists can still travel south to access the ramps. During Phase 2, which will begin around the middle of April, the southbound lanes will also be closed for 21 days for pavement tie-ins.

Other District 2 projects include a slope repair project near the intersection of State Route 163 and State Route 2, on the west end of Lakeshore Dr., and a traffic signal upgrade at the intersection of State Route 269 and State Route 163 in Marblehead. The new signals will feature flashing yellow arrows. When the yellow arrows are flashing, motorists should yield and then turn left when it is safe. When the yellow arrows are solid, motorists should prepare to stop.

The new traffic signals can increase safety at an intersection often used by tourists.

“It’s encouraging caution,” Hoagland said. “So many people driving through that intersection are not familiar with the area and have so many exciting things on their minds. It will increase safety.”

The yellow flashing arrow lights will be the first such lights installed in the Northwest Ohio.

“They are new for District 2,” Hoagland said.

Representatives from ODOT District 3 attended the event to address ongoing concerns about construction on Edison Bridge. District 3 Construction Engineer Mike Fair said lane closures will continue, but an end is in sight.

“There will continue to be intermittent lane closures while we put in permanent stripes and reflectors and do guardrail repair,” Fair said. “But there will be at least one-lane access and minimal ramp impacts.”

Fair said the Edison Bridge project is scheduled to be completed on Sept. 30, weather permitting.

Related Post 

0 Comments

Submit a Comment

Your email address will not be published. Required fields are marked *

Webify Ohio

Calendar

November 2026
SMTWTFS
1234567
891011121314
15161718192021
22232425262728
2930 






Share This